2 x 5 MVA 33/11 kVsub-station at Tolamamadi

- 33 kV
- —
- Tolamamadi, Sedam Taluk
- Kalaburagi
- Completed
Scope of work.
“Establishing 2 x 5 MVA, 33/11kv Sub Station in Tolamamadi in Sedam Tq & Dist Kalaburagi and Construction of 12 kms on TTK Basis”
- 2 x 5 MVA, 33/11 kV sub-station
- 12 km of line
- Sub-station
- 33 kV
- 33/11 kV
- Not stated
- Tolamamadi, Sedam Taluk
- Kalaburagi
- Completed
- 2016-17


Tolamamadi, Sedam Taluk
The location named in the record could not be geocoded, so this project is not placed on the map.
—
—
Kalaburagi district, Kalaburagi — 9 projects, district-level position