R-APDRP Part-B balanceworks, Sindhanur town

- Distribution
- GESCOM
- Sindhanur Town
- Raichur
- Completed
Scope of work.
“Execution of "Restructured Accelerated Power Development and Reforms Programme (R- APDRP) Part -B Balance Works in Bellary O & M Zone of GESCOM on PTK Basis. (SINDHANUR TOWN)”
- R-APDRP Part-B balance works
- Bellary O&M Zone
- Distribution
- GESCOM
- Sindhanur Town
- Raichur
- Completed
- 2016-17


Sindhanur Town
The location named in the record could not be geocoded, so this project is not placed on the map.
—
—
Raichur district, Raichur — 14 projects, 2 under execution, district-level position